Cladding Update

DB Facades produced a preliminary programme showing a) completion of all the detailed design and costing by the end of May 2026, b) a start on site of October 2026 and c) completion on site of Summer 2027. The major unknown in this programme is the Government’s Building Safety Regulator approval time that is the 18 week period between a) and b).

Ridge LLP, our project managers, have submitted a Planning Application to Portsmouth City Council. The description is “Replacement Cladding” On Existing Building(s).